Major Additions/Renovations

Cedar Creek Public School

Project Description  Classroom Addition, child care and family centre
Board Approval of Project  May 9, 2016
Project Status  Phase 2 of 4, Design, Funding received Nov 21, 2016
Projected Completion  Target – September 2019

Background:

 Grand River Collegiate Institute

Project Description  10 Classroom Addition and internal renovations
Board Approval of Project  May 11, 2015
Project Status  Phase 2 of 4, Design, Funding received Nov 21, 2016
Projected Completion  Target – September 2019

School location

Background:

  • May 9, 2016 – Capital Priorities Submission
  • October 30, 2015 – This project was not approved by the Ministry of Education for the 2015 Capital Priorities Grant
  • 2015 Capital Priorities Grant Submission – This project was submitted in the Board’s top 7 priorities to the Ministry of Education on July 15, 2015
  • May 11, 2015 – Capital Priorities Submission

Ryerson Public School

Project Description  8 Classroom Addition
Board Approval of Project  May 11, 2015
Project Status  Phase 2 of 4, Design, Funding received 21-Nov-2016
Projected Completion  Target – September 2019

School location

Background:

  • May 9, 2016 – Capital Priorities Submission
  • October 30, 2015 – This project was not approved by the Ministry of Education for the 2015 Capital Priorities Grant
  • 2015 Capital Priorities Grant Submission – This project was submitted in the Board’s top 7 priorities to the Ministry of Education on July 15, 2015
  • May 11, 2015 – Capital Priorities Submission

 John Mahood Public School

Project Description  Six classroom addition
Board Approval of Project  November 18, 2013
Project Status  Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding
Projected Completion  Unknown (no earlier than September 2020)

School location

Background:

 Waterloo-Oxford District Secondary School

Project Description  addition
Board Approval of Project  May 15, 2017
Project Status  Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding
Projected Completion  Unknown (no earlier than September 2020)

Background:

Parkway Public School

Project Description  addition
Board Approval of Project  May 15, 2017
Project Status  Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding
Projected Completion  Unknown (no earlier than September 2020)

Background:

Lackner Woods Public School

Project Description  Classroom addition and renovations (not FDK related)
Board Approval of Project  May 9, 2011
Project Status  Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding
Projected Completion  Unknown (no earlier than September 2019)

School location

Background:

  • May 15, 2017: This project is not being considered for the 2017 Capital Priorities Grant submission – it is not in the Board’s top 8 priorities
  • May 9, 2016: This project is not being considered for the 2016 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities.
  • May 11, 2015: This project is not being considered for the 2015 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities
  • April 25, 2014 – Ministry response to 2013 Capital Priorities Grant Submission
    • “The Ministry is supportive of the project but did not approve it at this time due to limited capital funding. The Ministry may consider it in the future”
  • 2013 Capital Priorities Grant Submission – This project is #7  in the Board’s top 8 priorities submitted for funding in the October 31, 2013, Capital Priorities Submission
  • Mach 18, 2013 – Revised boundary change timelines
  • January 24, 2013 – Ministry response to 2012 Capital Priorities Grant Submission
    • “This project was not considered for Capital Priorities Grant funding at this time. The board is requested to consider other schools/capacity in the area to manage this accommodation pressure.”

Lexington Public School

Project Description  Approx. 13 classroom addition and renovations to replace porta-pack classroom wing
Board Approval of Project  June 21, 2010
Project Status  Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding
Projected Completion  Unknown (no earlier than September 2020)

School location

Background:

  • May 15, 2017: This project is not being considered for the 2017 Capital Priorities Grant submission – it is not in the Board’s top 8 priorities
  • May 9, 2016: This project is not being considered for the 2016 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities.
  • May 11, 2015: This project is not being considered for the 2015 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities
  • April 25, 2014 – Ministry response to 2013 Capital Priorities Grant Submission
    • “This project is not identified as a priority from a provincial perspective”
  • 2013 Capital Priorities Grant Submission – This project is #8  in the Board’s top 8 priorities submitted for funding in the October 31, 2013, Capital Priorities Submission
  • April 30, 2013: Update regarding Lexington P.S. addition and new school construction
  • January 24, 2013 – Ministry response to 2012 Capital Priorities Grant Submission
    • “This project was not considered for Capital Priorities Grant funding as it was identified as a lower priority by the board.”