Major Additions/Renovations
Cedar Creek Public School
Project Description | Classroom Addition, child care and family centre |
Board Approval of Project | May 9, 2016 |
Project Status | Phase 2 of 4, Design, Funding received Nov 21, 2016 |
Projected Completion | Target – September 2019 |
Background:
- May 9, 2016 – Capital Priorities Submission
Grand River Collegiate Institute
Project Description | 10 Classroom Addition and internal renovations |
Board Approval of Project | May 11, 2015 |
Project Status | Phase 2 of 4, Design, Funding received Nov 21, 2016 |
Projected Completion | Target – September 2019 |
Background:
- May 9, 2016 – Capital Priorities Submission
- October 30, 2015 – This project was not approved by the Ministry of Education for the 2015 Capital Priorities Grant
- 2015 Capital Priorities Grant Submission – This project was submitted in the Board’s top 7 priorities to the Ministry of Education on July 15, 2015
- May 11, 2015 – Capital Priorities Submission
Ryerson Public School
Project Description | 8 Classroom Addition |
Board Approval of Project | May 11, 2015 |
Project Status | Phase 2 of 4, Design, Funding received 21-Nov-2016 |
Projected Completion | Target – September 2019 |
Background:
- May 9, 2016 – Capital Priorities Submission
- October 30, 2015 – This project was not approved by the Ministry of Education for the 2015 Capital Priorities Grant
- 2015 Capital Priorities Grant Submission – This project was submitted in the Board’s top 7 priorities to the Ministry of Education on July 15, 2015
- May 11, 2015 – Capital Priorities Submission
John Mahood Public School
Project Description | Six classroom addition |
Board Approval of Project | November 18, 2013 |
Project Status | Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding |
Projected Completion | Unknown (no earlier than September 2020) |
Background:
- May 15, 2017 – Capital Priorities Submission
- This project was not approved by the Ministry of Education for the 2016 Capital Priorities Grant
- May 9, 2016 – Capital Priorities Submission
- October 30, 2015 – This project was not approved by the Ministry of Education for the 2015 Capital Priorities Grant
- 2015 Capital Priorities Grant Submission – This project was submitted in the Board’s top 7 priorities to the Ministry of Education on July 15, 2015
- May 11, 2015 – Capital Priorities Submission
- November 18, 2013: Elementary Schools Boundary Study Report – Elmira
Waterloo-Oxford District Secondary School
Project Description | addition |
Board Approval of Project | May 15, 2017 |
Project Status | Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding |
Projected Completion | Unknown (no earlier than September 2020) |
Background:
- May 15, 2017 – Capital Priorities Submission
Parkway Public School
Project Description | addition |
Board Approval of Project | May 15, 2017 |
Project Status | Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding |
Projected Completion | Unknown (no earlier than September 2020) |
Background:
- May 15, 2017 – Capital Priorities Submission
Lackner Woods Public School
Project Description | Classroom addition and renovations (not FDK related) |
Board Approval of Project | May 9, 2011 |
Project Status | Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding |
Projected Completion | Unknown (no earlier than September 2019) |
Background:
- May 15, 2017: This project is not being considered for the 2017 Capital Priorities Grant submission – it is not in the Board’s top 8 priorities
- May 9, 2016: This project is not being considered for the 2016 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities.
- May 11, 2015: This project is not being considered for the 2015 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities
- April 25, 2014 – Ministry response to 2013 Capital Priorities Grant Submission
- “The Ministry is supportive of the project but did not approve it at this time due to limited capital funding. The Ministry may consider it in the future”
- 2013 Capital Priorities Grant Submission – This project is #7 in the Board’s top 8 priorities submitted for funding in the October 31, 2013, Capital Priorities Submission
- Mach 18, 2013 – Revised boundary change timelines
- January 24, 2013 – Ministry response to 2012 Capital Priorities Grant Submission
- “This project was not considered for Capital Priorities Grant funding at this time. The board is requested to consider other schools/capacity in the area to manage this accommodation pressure.”
Lexington Public School
Project Description | Approx. 13 classroom addition and renovations to replace porta-pack classroom wing |
Board Approval of Project | June 21, 2010 |
Project Status | Phase 1 of 4, Pre-Design, awaiting Ministry of Education approval and funding |
Projected Completion | Unknown (no earlier than September 2020) |
Background:
- May 15, 2017: This project is not being considered for the 2017 Capital Priorities Grant submission – it is not in the Board’s top 8 priorities
- May 9, 2016: This project is not being considered for the 2016 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities.
- May 11, 2015: This project is not being considered for the 2015 Capital Priorities Grant submission – it is not in the Board’s top 7 priorities
- April 25, 2014 – Ministry response to 2013 Capital Priorities Grant Submission
- “This project is not identified as a priority from a provincial perspective”
- 2013 Capital Priorities Grant Submission – This project is #8 in the Board’s top 8 priorities submitted for funding in the October 31, 2013, Capital Priorities Submission
- April 30, 2013: Update regarding Lexington P.S. addition and new school construction
- January 24, 2013 – Ministry response to 2012 Capital Priorities Grant Submission
- “This project was not considered for Capital Priorities Grant funding as it was identified as a lower priority by the board.”